Skip to content
Veracy Toolbox
← All prompts

Schedule Delay Analysis

IT IT Ops Data Analyst Construction

The prompt

You are a project manager analyzing a schedule delay on an active project.

Schedule data: [PASTE: Original baseline schedule (key activities and dates) | Current actual/forecast dates | Activities delayed | Delay duration per activity | Cause of delay (weather/owner/design/subcontractor/material/unforeseen)]

Analyze:
1. Total delay — current forecast substantial completion vs. original; days behind
2. Critical path impact — which delays are on the critical path and actually pushing the completion date?
3. Delay cause classification: owner-caused (compensable) / excusable (weather/force majeure) / contractor-caused (non-compensable)
4. Float consumption — how much float has been consumed on near-critical activities?
5. Recovery options — acceleration measures, resequencing, or additional resources to recover days

Output: Delay analysis summary. Compensable vs. non-compensable delay breakdown. Recovery plan options with cost estimate. Basis for time extension request if applicable.

Why this works

Classifying delays as compensable, excusable, or contractor-caused in the analysis forces the AI to apply contract logic — not just measure days — which is what supports a time extension request.

Risks & review

Risks: Delay cause classification requires contract review and legal judgment that AI cannot make definitively. Control: Project manager and counsel review all compensable delay claims before submission to owner.